Pour Strip Zero
IU Health Downtown Hospital Rendering

Project Information

Partners:

MKA & Gilbane

Industry:

Healthcare

Schedule Acceleration:

5 Months

Cost Savings:

Over $2.5M Dollars

Time Saved. Costs Cut. Pour Strips Elminated.

At the IU Health Downtown Hospital, the structural engineers from MKA made the strategic decision to specify PS=Ø from the start—eliminating all traditional pour strips across this massive, high-profile hospital project (at the time, the largest active healthcare construction project in the country).

The result? A staggering 5 months of schedule acceleration and $2.5 million in cost savings.

By removing pour strips entirely, the team avoided time-consuming backshoring, pour backs, and rework—unlocking cleaner sequencing, faster trade access, and major efficiency gains across the structure. From early design through final pour, PS=Ø helped streamline coordination and deliver results at scale.

The IU Health project proves the value of early adoption: when PS=Ø is engineered in from the beginning, the impact is transformational—on time, cost, safety, and quality.

Benefits Delivered

Eliminated Traditional Pour Strips Eliminated Traditional Pour Strips
5 Months of Schedule Acceleration 5 Months of Schedule Acceleration
Increased Jobsite Efficiency Increased Jobsite Efficiency
Eliminated Backshoring Eliminated Backshoring
Over $2.5M in Cost Savings Over $2.5M in Cost Savings
Improved Jobsite Safety Improved Jobsite Safety
Large Beams and Girders in this Reinforced Concrete structure Couplers installed on bulkhead with Beams and Girders Final PS=Ø Slab Seam